Challenges
The was limited availability of drawings and accurate data of the existing building. Site surveys had to be taken after start on site, as areas of the existing structure were exposed.
Detailed design coordination was necessary with the curtain wall subcontractor.
The intersection of the new higher, four-storey extension with the existing profile of the corner tower, was complicated.
Due to the tight city centre site, storage space was highly restricted, which required additional logistics planning.
The client set demanding sustainability targets to optimise energy efficiency, and reduce operational and embodied carbon emissions.
The facade had to be passive fire-engineered for safety.
Solutions
A2O developed bay studies and retained design resources throughout in order to adjust the design as the project progressed and as the existing structure was exposed.
A2O worked closely with the curtain wall installer to develop interface details.
The geometry of the interface of the new extension and existing corner required particular attention in detailing the design.
A number of small ‘just in time’ deliveries had to be made, with planned dates adjusted to suit progress on site.
Building envelope performance was enhanced with the new windows, extra insulation to soffits and more. The retrofit obtained BREEAM Outstanding.
The facade was installed to the passive fire standard LPS 1531.
Fact File
Sector
- Offices
STATUS
- Refurbishment
Value
- £950,000
Scope of Work
- Brick Slip
- Architectural Panels (fibre-cement) to entrance
- PPC Aluminium plank with bronze finish, as fascias to glazed areas
- A1 fire-rated rainscreen slab Insulation
- Fire Barriers
- SFS & Board
- Copings