Challenges
The biggest challenge was the late-stage design handover, leaving a pre-construction programme of only 3 weeks due to another cladding contractor suddenly going into administration while on the job.
Due to taking over in later stage pre-construction, some materials already specified had to be used, although not the most practical and install-friendly.
The site team found the vents had been installed in the wrong locations, disrupting the tile layout.
Completing on time was the largest challenge, given the ultra short lead-in and the issues on site.
The challenge was to keep on budget, despite the extremely limited duration of the design phase.
As a regeneration project with new homes for a wide diversity of households, the main contractor Hill had a multi-faceted Social Value Plan.
Solutions
A²O managed to keep the project on track despite the extremely tight time frame, thanks to proactive problem solving and the design team’s strong supply partner relationships.
The pre-specified insulation was not as rigid as the standard rainscreen slab normally used, which required more dexterity from the install team.
The site team had to cut a lot more tiles to work around the vents to retain the desired aesthetic.
The site team carried out site surveys to reduce rework and facilitate smooth execution.
A²O installers suggested design simplifications that reduced installation time and material costs.
A²O partnered with the Social Value plan, with an apprentice working on the design of the facade and contributions to the food bank & Christmas Appeal.
Fact File
Sector
- Residential
STATUS
- New Build
Value
- £2,750,000
Scope of Work
- Terracotta Rainscreen
- Aluminium Panels
- Stone Wool Facade Panels
- Bracketry
- Rainscreen Slab Insulation
- Fire Barriers
- Cappings & Flashings